Pelham: Community Centre on schedule within budget

Posted Apr 30th, 2018 in Municipal, Sports and Recreation, fonthill

Pelham: Community Centre on schedule within budget

The Niagara Story Place sponsored by Calhoun

Mayor Dave Augustyn's weekly column. 

A couple of weeks ago, Bill Gibson, Chair of Pelham’s Meridian Community Centre Oversight Committee, presented another upbeat update to Council.

You will recall that Council listened to suggestions from the public for proper project supervision by establishing Community Centre Oversight Committee two years ago. The committee includes two community members (Gibson and Bill Sheldon), one Council rep (Councillor Accursi), and the Chief Administrative Officer (Darren Ottaway). This committee works to ensure that the Town receives value-for-money in every aspect of the project and that the project gets delivered on time and on budget, and to provide the community with consistent and timely updates.

You will also recall that Ball Construction serves as the project’s construction manager and works with the committee, the architect, Town staff, and the various contractors to manage the project’s timing and construction.

Mr. Gibson provided updates on the project’s milestones, and finances. He showed pictures of the significant progress on the Meridian Community Centre. He outlined that the rink boards, glass, and netting were already installed in the Duliban Insurance Arena. He showed the painting and finishing work in the activity centres (named the Lucchetta Homes Courts). He spoke about the great work of local contractors – like Star Tile, which has tiled each of the washrooms and change rooms. He showed photos of the glass along the Walker Industries Upper Viewing Galleria and around the Mountainview Homes Upper Arena Lobby. He outlined improvement in the Dr. Gary & Mal Accursi multi-purpose room. His pictures showed progress along the Lookout Ridge Walking / Running Track and final preparations for the 1,000 seats in the Accipiter Arena.

He also outlined some imminent construction milestones like installing the basketball nets and divider curtains in the activity centre and installing the centre scoreboard in the Accipiter Arena. He said that most of the porcelain tile floors on the second floor would be completed by the end of April and, depending on the moisture levels, Ball Construction would also oversee the start of the wood floor installation in the activity centre. Later in May, workers would commence installation of the rubber “skaters” flooring and the poured rubber walking / running track floor.

Mr. Gibson said that the Oversight Committee was forecasting that this project will be within budget and will reach substantial completion on time – on June 1, 2018.

“Substantial completion” means that Ball Construction will “turn over the keys” to Town staff. Over the summer, staff will re-test systems, move in furniture and equipment and work with volunteer user groups so they can move furniture and equipment into their rooms and storage spaces. We are also planning for tours and open houses over the summer – but they have yet to be scheduled.

Obviously, all of this is great news for our community! Council and I look forward to opening the new Meridian Community Centre so that it can become the place for residents of all ages to gather and enjoy a wide-variety of recreational, social, health and community activities for many, many years.

To review the presentation by the Oversight Committee, please click here. You may contact Mayor Dave at mayordave@pelham.ca .

This message could be about your business. Ask us.

  • A great community service to keep everyone informed. Thank you for this!
    Louise M.

GET CONNECTED IN NIAGARA. ADVERTISE WITH CONNECTING NIAGARA!

Powered by PRowl Communications

9053215097 Contact